Iowa energy center grant program, ch 404
ARC 8072C
ECONOMIC DEVELOPMENT AUTHORITY[261]
Adopted and Filed
Rulemaking related to Iowa energy center grant program
The Iowa Energy Center Board (Board) hereby rescinds Chapter 404, "Iowa Energy Center Grant Program," Iowa Administrative Code, and adopts a new chapter with the same title.
Legal Authority for Rulemaking
This rulemaking is adopted under the authority provided in Iowa Code section 15.120.
State or Federal Law Implemented
This rulemaking implements, in whole or in part, Iowa Code section 15.120.
Purpose and Summary
Pursuant to Executive Order 10 (January 10, 2023), the Board has rescinded Chapter 404 relating to the Iowa Energy Center grant program and adopted a new chapter in lieu thereof. The new chapter eliminates language that is duplicative of statutory language. Additionally, the following changes from the existing chapter have been made:
●Rule 261—404.1(15) was updated to remove unnecessary definitions and be more concise.
●Rule 261—404.2(15) was updated to be more concise. Additionally, paragraph 404.3(6)"d" was updated so that private asset development is an eligible project. Such projects are subject to limitations imposed by the rewritten paragraph (which excludes projects that entail improvements to existing buildings) and changes to rule 261—404.4(15).
●Rule 261—404.3(15) was updated for clarity.
●Rule 261—404.4(15) was updated to be more concise and to address equipment purchases.
●Rule 261—404.5(15) was updated to allow for use of application websites other than iowagrants.gov and to correct the Economic Development Authority's website. The review criteria were updated to reflect evaluation of project sustainability in addition to dissemination of project results. The updated rule no longer mandates a preapplication process. The updated rule also eliminates the necessity for the Board to deny or defer applications that are not approved for awards.
●Rule 261—404.6(15) was updated to be more concise and to increase the minimum dollar amount for disbursement requests from $500 to $1,000.
Public Comment and Changes to Rulemaking
Notice of Intended Action for this rulemaking was published in the Iowa Administrative Bulletin on April 3, 2024, as ARC 7746C. Public hearings were held on April 23 and 29, 2024. No one attended the public hearings. No public comments were received. No changes from the Notice have been made.
Adoption of Rulemaking
This rulemaking was adopted by the Board on May 16, 2024.
Fiscal Impact
This rulemaking has no fiscal impact to the State of Iowa.
Jobs Impact
After analysis and review of this rulemaking, no impact on jobs has been found.
Waivers
Any person who believes that the application of the discretionary provisions of this rulemaking would result in hardship or injustice to that person may petition the Board for a waiver of the discretionary provisions, if any, pursuant to 261—Chapter 199.
Review by Administrative Rules Review Committee
The Administrative Rules Review Committee, a bipartisan legislative committee which oversees rulemaking by executive branch agencies, may, on its own motion or on written request by any individual or group, review this rulemaking at its regular monthly meeting or at a special meeting. The Committee's meetings are open to the public, and interested persons may be heard as provided in Iowa Code section 17A.8(6).
Effective Date
This rulemaking will become effective on July 31, 2024.
The following rulemaking action is adopted:
Item 1. Rescind 261—Chapter 404 and adopt the following new chapter in lieu thereof:
CHAPTER 404
IOWA ENERGY CENTER GRANT PROGRAM
261—404.1(15) Definitions.
"Activity" means one or more specific activities, projects or programs associated with Iowa energy center grant funds.
"Authority" means the economic development authority created in Iowa Code section 15.105.
"Board" means the governing board of the Iowa energy center established pursuant to Iowa Code section 15.120(2).
"Co-investigator" means a person who shares the responsibility of conducting grant activities with the principal investigator of a project.
"Funding announcement" means a publicly available document that contains the official information for a grant, including the application deadline, goals of the activity, eligibility, reporting, availability of funds and instructions on applying for the grant.
"Iowa energy center" or "IEC" means the Iowa energy center established by Iowa Code section 15.120.
"Principal investigator" means a person with the primary responsibility for conducting research.
"Recipient" means an organization that was awarded an Iowa energy center grant.
"Subrecipient" means an organization contracting with and receiving funds from a recipient to carry out IEC grant activities.
261—404.2(15) Eligibility.
404.2(1) Eligible applicants are identified in Iowa Code section 15.120(3)"a."
404.2(2) Any eligible applicant may submit an application that includes one or more subrecipients. The board may limit the amount of an award that a subrecipient can receive.
404.2(3) Any eligible applicant may apply individually or jointly with another eligible applicant or other eligible applicants.
404.2(4) A principal investigator will be allowed to submit one application per funding announcement. An applicant who has submitted an application as the principal investigator for a funding announcement may also be named as a co-investigator on one additional application submitted for the same funding announcement.
404.2(5) Requirements for IEC grant awards include but are not limited to the following:
a. Applicants shall demonstrate a benefit for ratepayers.
b. Applicants shall demonstrate that they are eligible candidates.
c. Applicants shall demonstrate the capacity for grants administration.
d. Applicants who have previously received Iowa energy center awards shall have demonstrated acceptable past performance, including the timely expenditure of funds.
e. Applicants shall demonstrate the feasibility of completing the proposed activities with the funds requested.
f. Applicants shall identify and describe any other sources of funding for the proposed activities.
404.2(6) The following types of projects are ineligible:
a. Relocation of a business.
b. Expansion of a business.
c. Funding for existing training programs.
d. Improvements to existing buildings, including energy efficiency or energy generation projects.
e. Pipeline, transmission line, and distribution line construction.
f. First generation ethanol.
g. Cellulosic ethanol.
261—404.3(15) Funding and award terms.
404.3(1) For each fiscal year that funds are available, the board will determine the amount of funds available to be awarded as grants in that fiscal year.
404.3(2) If any funds are allocated to a specific grant activity but are not awarded after a funding cycle, the board may reallocate those funds to a different grant activity.
404.3(3) The board may reallocate any recaptured funds to a different grant activity.
404.3(4) The maximum grant award is $1 million per application. The minimum grant award is $10,000 per application.
404.3(5) The initial duration of a grant agreement will be no longer than three years. However, a recipient may apply for a no-cost extension of an agreement. If the approval of a no-cost extension would cause the duration of the grant agreement to exceed five years, the no-cost extension will not be granted.
261—404.4(15) Project budget.
404.4(1) Only expenditures directly related to the implementation of the funded grant activity will be reimbursed. Vehicle and equipment purchases are eligible only when the purchase is an integral part of the funded grant activity and must be approved by the board at the time the award is made.
404.4(2) Ineligible expenses include but are not limited to:
a. Purchase or rental of buildings.
b. Office equipment.
c. Furniture and fixtures.
d. Intangible assets.
e. International travel.
f. Insurance.
g. Phone expenses.
404.4(3) Other budget requirements include the following:
a. Indirect costs shall not exceed more than 20 percent of a grant award.
b. IEC grant funds shall not be used as cost share to a federal grant award.
c. Vehicle and equipment purchases or other expenses relating to vehicles or equipment are not eligible if the purchase or expense supports the proposed grant activity but is not an integral part of the proposed grant activity. If a vehicle or equipment purchase is an integral part of a grant activity but a recipient fails to obtain board approval prior to the purchase, then the purchase is ineligible.
261—404.5(15) Application process and review.
404.5(1) The board will issue funding announcements for grant applications at least once per fiscal year, provided funds are available.
404.5(2) Application forms will be available at iowagrants.gov or another website as identified by the authority.
404.5(3) Applications will only be accepted during the established application period, as identified at www.iowaeda.com.
404.5(4) Review criteria may include but are not limited to:
a. The proposed project demonstrates a need for further research, development, training or pilot projects.
b. The proposed project provides a benefit to ratepayers.
c. The application has a well-developed budget that is relevant to the project and that provides documentation of planned project expenses.
d. The application describes a plan for the dissemination of project results or to sustain the project after the grant period ends.
404.5(5) The authority may require applicants to submit a preapplication to determine eligibility and competitiveness for the program.
404.5(6) The authority will review applications for completeness, eligibility, and technical and financial merit. The authority may engage an outside technical review panel to complete technical review of applications. The authority will prepare recommendations for the grant committee. The grant committee will review staff recommendations, score applications, and make recommendations to the board. Upon review of the recommendations of the grant committee, the board may approve grant awards.
261—404.6(15) Administration.
404.6(1) Notice of approval and agreement execution. The authority will notify successful applicants in writing of an approved request for funding. After notifying the recipient of an award, the authority will prepare an agreement that reflects the terms of the award. The recipient must execute and return the agreement to the authority within 60 days of the transmittal of the final agreement from the authority. Failure to do so may be cause for the board to terminate the award.
404.6(2) Disbursement of funds. Recipients shall submit requests for grant funds in the manner prescribed by the authority. Disbursements shall be made on a reimbursement basis. No advance disbursements shall be allowed. Disbursements may be withheld if applicable performance reports have not been received and approved. Individual requests for funds shall be made in an amount equal to or greater than $1,000 per request, except for the final draw of funds.
404.6(3) Recordkeeping and retention. Recipients shall retain all financial records, supporting documents and all other records pertinent to the grant for five years after agreement closeout.
404.6(4) Performance reports and reviews. Recipients shall submit performance reports to the authority as described in the agreement executed pursuant to subrule 404.6(1). The authority may perform project reviews and site inspections as necessary to ensure program compliance.
404.6(5) Agreement amendments.
a. Any substantive change to a funded IEC project, including time extensions, budget revisions, and alterations to proposed activities, will be considered an agreement amendment. The recipient shall request an amendment in writing. No amendment shall be valid until approved by the board, except as provided in paragraph 404.6(7)"b" and confirmed in writing by the authority.
b. Staff approvals.
(1)Staff may approve one no-cost extension provided that the extension complies with subrule 404.3(5). Additional no-cost extensions shall be presented to the board for approval.
(2)Budget modifications. Any substantial modification of a project budget shall require board approval. Staff may approve budget modifications that are not substantial. For purposes of this subparagraph, "substantial modification" means a budget modification of either $10,000 or 10 percent of the total grant award, whichever is less.
404.6(6) Agreement closeout. Upon agreement expiration or project completion, the authority will initiate project closeout procedures.
404.6(7) Compliance with state and local laws and rules. Recipients shall comply with these rules, with any applicable provisions of the Iowa Code, and with any applicable local rules.
404.6(8) Noncompliance. At any time during a project, the IEC may, for cause, find that a recipient is not in compliance with the requirements of this program. At the board's discretion, remedies may include penalties up to and including the return of grant funds to the IEC. Findings of noncompliance may include the use of Iowa energy center funds for activities not described in the application; failure to complete approved activities in a timely manner; failure to comply with any applicable state or federal rules, regulations, or laws; or the lack of a continuing capacity of the recipient to carry out the approved project in a timely manner.
These rules are intended to implement Iowa Code section 15.120.
[Filed 5/31/24, effective 7/31/24]
[Published 6/26/24]
Editor's Note: For replacement pages for IAC, see IAC Supplement 6/26/24.
The official published PDF of this document is available from the Iowa General Assembly’s Administrative Rules page.
View the Iowa Administrative Bulletin for 6/26/2024.
The following administrative rule references were added to this document. You may click a reference to view related notices.
Rule 261-404.1 Rule 261-404.2 Rule 261-404.3 Rule 261-404.3(5) Rule 261-404.4 Rule 261-404.5 Rule 261-404.6 Rule 261-404.6(1) Rule 261-404.6(7)The following Iowa code references were added to this document. You may click a reference to view related notices.
Iowa Code 15.105 Iowa Code 15.120 Iowa Code 15.120(2) Iowa Code 15.120(3)The following keywords and tags were added to this document. You may click a keyword to view related notices.
Administration Agreement amendments Agreement closeout Application process and review Compliance with state and local laws and rules Definitions Disbursement of funds Eligibility Funding and award terms Noncompliance Notice of approval and agreement execution Performance reports and reviews Project budget Recordkeeping and retention© 2024 State of Iowa | Privacy Policy